Installation of output breakers maintenance - nLighten, Chester - 16th-19th of November, 2026

Scheduled for Nov 16, 09:00 UTC  -  Nov 19, 15:00 UTC

Scheduled

Maintenance window: 16/11/2026 08:00 - 19/11/2026 14:00 UTC

Installation of output breakers on SW/BD's 1,2,3,5 requires SW/BD's to be isolated. The vendor has estimated a period of four hours per SW/BD.
16/11/2026: SW/BD 1 will be isolated.
This will remove 1N power supply to the listed ND cabinets within data hall 2.
Row 1 cabs 1,2,3,6,8,11,13,14,15,18,20,23,25,26,27,30,32,35
Row 2 cabs 2,5,7,8,9,12,14,17,19,20,21,24,26,29,31,32,33,36

17/11/2026 SW/BD 2 will be isolated.
This will remove 1N power supply to the listed ND cabinets within data hall 2.
Row 1 cabs 1,4,5,6,9,12,13,16,17,18,21,24,25,28,29,30,33,36
Row 2 cabs 3,6,7,10,11,12,15,18,19,22,23,24,27,30,31,34,35,36

18/11/2026 SW/BD 3 will be isolated.
This will remove 1N power supply to the listed ND cabinets within data hall 2.
Row 1 cabs 2,4,7,8,9,10,14,16,19,20,21,22,26,28,31,32,33,34
Row 2 cabs 1,2,3,4,8,10,13,14,15,16,20,22,25,26,27,28,32,34

19/11/2026 SW/BD 5 will be isolated.
This will remove 1N power supply to the listed ND cabinets within data hall 2.
Row 1 cabs 3,5,7,10,11,12,15,17,19,22,23,24,27,29,31,34,35,36
Row 2 cabs 1,4,5,6,9,11,13,16,17,18,21,23,25,28,29,30,33,35


If you have any questions, please contact the support team via the ticket portal or email (cloud-support@taigacloud.com)
Posted Oct 12, 2026 - 06:59 UTC