Maintenance window: 16/11/2026 08:00 - 19/11/2026 14:00 UTC
Installation of output breakers on SW/BD's 1,2,3,5 requires SW/BD's to be isolated. The vendor has estimated a period of four hours per SW/BD. 16/11/2026: SW/BD 1 will be isolated. This will remove 1N power supply to the listed ND cabinets within data hall 2. Row 1 cabs 1,2,3,6,8,11,13,14,15,18,20,23,25,26,27,30,32,35 Row 2 cabs 2,5,7,8,9,12,14,17,19,20,21,24,26,29,31,32,33,36
17/11/2026 SW/BD 2 will be isolated. This will remove 1N power supply to the listed ND cabinets within data hall 2. Row 1 cabs 1,4,5,6,9,12,13,16,17,18,21,24,25,28,29,30,33,36 Row 2 cabs 3,6,7,10,11,12,15,18,19,22,23,24,27,30,31,34,35,36
18/11/2026 SW/BD 3 will be isolated. This will remove 1N power supply to the listed ND cabinets within data hall 2. Row 1 cabs 2,4,7,8,9,10,14,16,19,20,21,22,26,28,31,32,33,34 Row 2 cabs 1,2,3,4,8,10,13,14,15,16,20,22,25,26,27,28,32,34
19/11/2026 SW/BD 5 will be isolated. This will remove 1N power supply to the listed ND cabinets within data hall 2. Row 1 cabs 3,5,7,10,11,12,15,17,19,22,23,24,27,29,31,34,35,36 Row 2 cabs 1,4,5,6,9,11,13,16,17,18,21,23,25,28,29,30,33,35
If you have any questions, please contact the support team via the ticket portal or email (cloud-support@taigacloud.com)