This is a notice to inform you about additional maintenance that will be performed at Lefdal Mine Data Centers (LMD) from week 44-46 this year.

Dedicated resources (internal and external) have been assigned to perform the work and supervise the completion of this project.

The planned work on our cooling system will commence on October 27thand be completed on November 10th.

During this time frame newly installed pumps and heat exchangers will be commissioned, tested and eventually included in the production environment.

On Monday October 27th (week 44) Lefdal will transition over to two new heat exchangers (3 and 4) on cooling system A.

On November 04th and 05th, Lefdal transition over to heat exchange 3 and 4 on cooling system B.

Following these two activities, Lefdal will perform comprehensive testing of the systems on November 05th and November 10th.

The planned work is not expected to have any operational impact.