Start Campus (Portugal) Upcoming Maintenance - 01-26 Oct

Scheduled Maintenance Report for Taiga Cloud status page

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 01, 2026 - 00:00 UTC

Scheduled

Start Campus (Portugal) Upcoming Maintenance - 01-26 Oct

1M - Generators Run 2026-10
01/10/2026 00:00 - 01/10/2026 16:00

1M - PM - SSF – PCW - Side Stream Filtration 2026-10
01/10/2026 00:00 - 01/10/2026 02:00

1M - PM - SSF - CT – Side Stream Filtration 2026-10
01/10/2026 00:00 - 01/10/2026 03:00

3M - PM - Vacuum Degasser 2026-10
01/10/2026 00:00 - 01/10/2026 02:00

3M - PM - HUM - Humidification 2026-10
01/10/2026 00:00 - 01/10/2026 02:00

1Y - PM - CT - Cooling Tower 2026
01/10/2026 00:00 - 01/10/2026 12:00

1Y - PM - WCC - Water Cooled Chiller 2026
01/10/2026 00:00 - 01/10/2026 12:00

6M - PM - Heat Exchanger Free Cooling Plate Heat Exchanger 2026-10
01/10/2026 00:00 - 01/10/2026 03:00

3M - Nautilus Pipework
01/10/2026 00:00 - 01/10/2026 01:00

3M - Nautilus Pipework
01/10/2026 00:00 - 01/10/2026 01:00

3M - PM - CDU/RDU control system
01/10/2026 00:00 - 01/10/2026 01:00

3M - CDU - Maintenance 2026-10 - NORTH
01/10/2026 00:00 - 01/10/2026 06:00

3M - CDU - Maintenance 2026-10 - SOUTH
01/10/2026 00:00 - 01/10/2026 06:00

1M - PM - Seawater Filter - Wedeco 2026-10
01/10/2026 00:00 - 01/10/2026 02:00

1M - PM - Seawater Sampling
01/10/2026 00:00 - 01/10/2026 02:00

1Y - PM - MV - RMU Early/Offsite Sea Water Station 2026
01/10/2026 00:00 - 01/10/2026 01:00

1Y - PM - Dry-type Transformers seawater
01/10/2026 00:00 - 01/10/2026 01:00

1Y - PM - MV - RMU seawater 2026
01/10/2026 00:00 - 01/10/2026 01:30

6M - PM - Seawater Pump Cleaning 2026-10
01/10/2026 00:00 - 01/10/2026 05:00

1Y - PM - LV Distribution Board UPS M3
01/10/2026 00:00 - 01/10/2026 06:00

1Y - PM - Dry-type Transformers Substation 2026
01/10/2026 00:00 - 01/10/2026 04:00

3M - PM - Fire hose reels
01/10/2026 00:00 - 01/10/2026 05:00

1Y - PM - Split - Air Conditioner Substation 2026
01/10/2026 00:00 - 02/10/2026 12:01

6M - PM - Seawater Submerged Pump 2026-10
01/10/2026 00:00 - 01/10/2026 05:00

3 Monthly RDC maintenance 2026-10
01/10/2026 00:00 - 01/10/2026 03:36

3M - PM - Air Handling Units (AHUs/DOAs) Mechanical Space
01/10/2026 08:00 - 01/10/2026 09:00

3M - PM - Air Handling Units (AHUs/DOAs) DH 2A
01/10/2026 08:00 - 01/10/2026 09:00

3M - PM - Air Handling Units (AHUs/DOAs) DH 2B
01/10/2026 08:00 - 01/10/2026 09:00

1M - PM - ACC - Air Cooled Chiller 2026-10
01/10/2026 15:04 - 01/10/2026 17:04

1Y - PM - HV Transformers (25MVA) 2026
04/10/2026 08:00 - 04/10/2026 10:00

1W - Fire Pumps tests
05/10/2026 08:00 - 05/10/2026 09:00

6M - PM - UPS Systems M4 2026-9
05/10/2026 08:00 - 05/10/2026 16:00

3M - PM - Fire Extinguishers 01_50
05/10/2026 09:00

3M - PM - Fire Extinguishers 100_145
05/10/2026 09:00 - 05/10/2026 10:30

3M - PM - Fire Extinguishers 100_145
05/10/2026 09:00

3M - PM - Fire Extinguishers 100_145
05/10/2026 09:00 - 05/10/2026 09:06

3M - PM - Fire Extinguishers 51_100
05/10/2026 09:00

1W - PM - CT - Cooling Tower 2026-41
05/10/2026 16:25 - 05/10/2026 19:25

1W - Fire Pumps tests
12/10/2026 08:00 - 12/10/2026 09:00

3M - PM - Fire hose reels
12/10/2026 09:00 - 12/10/2026 21:30

1W - PM - CT - Cooling Tower 2026-42
12/10/2026 16:25 - 12/10/2026 19:25

1W - Fire Pumps tests
19/10/2026 08:00 - 19/10/2026 09:00

1W - PM - CT - Cooling Tower 2026-43
19/10/2026 16:25 - 19/10/2026 19:25

1W - Fire Pumps tests
26/10/2026 08:00 - 26/10/2026 09:00

1W - PM - CT - Cooling Tower 2026-44
26/10/2026 16:25 - 26/10/2026 19:25



If you have any concerns during this maintenance window, please contact Taiga Cloud Customer Support via the ticket portal or email cloud-support@taigacloud.com.
Posted Sep 21, 2026 - 11:23 UTC