HV Maintenance N01 Campus Week 42

Scheduled Maintenance Report for Taiga Cloud status page

Completed

The scheduled maintenance has been completed.
Posted Oct 16, 2026 - 17:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 12, 2026 - 06:00 UTC

Scheduled

The work will include transferring electrical supplies from HVS1 to HVS2. During the switching period, selected electrical systems will be temporarily de-energised, including:

Power supplies associated with DCM102, DCM101 and DCM122, SH1 and SH2

Selected 22 kV distribution boards and high-voltage low-level systems
During the work, the affected data centre systems will temporarily operate with N+1 power availability through utility power and generator backup, rather than the normal 2N utility configuration. The work is planned and controlled, and no interruption to customer IT loads is expected.
For the SH (Security House) buildings, the power feed will be:
Week42, SH1 will only have B feed, with generator
Week 45 , SH2 will only have A feed, with generator
Planned date and time:
Week 42, start Monday 12th of October switching from HVS2 to HVS1
Week 45, start Monday 2nd of November switching from HVS1 to HVS2


Expected duration: two week, week 42 and 45
Our operations team will monitor the electrical infrastructure throughout the activity and restore the normal configuration once the work has been completed and verified.
Please contact your usual Bulk representative if you have any questions or require further information.


Location: N01 Campus


Start time and date: 2026-10-12 08:00 CEST
Stop time and date: 2026-10-16 19:00 CEST
Posted Oct 05, 2026 - 15:09 UTC