Power station B maintenance GlobalSwitch London East

Scheduled for Oct 23, 08:00 UTC  -  Nov 25, 18:00 UTC

Scheduled

Maintenance Window:
23rd October - 25th November 2025

Location & Affected Areas:
• Site: nLighten GlobalSwitch London East - United Kingdom
• Impacted Area: UK E01

As GlobalSwitch London East approach our migration to facilitate the removal of Level 5 from the DRUPS backed system onto the more efficient generator and SUPS backed systems , there will be periods of reduced resilience .
The attached documentation explains this along with theit timelines for undertaking the works.
Essentially, we have 2 periods at approximately 2-3 weeks each commencing October 23rd through to the end of November.

Isolation of PSS /5/A from Power station B ( 23rdOctober – 9thNovember )
The first period commencing 24 th October through to 9 th November will be isolating the ‘A’ HV supply from the A power station and running on the B supply only . This is considered a minimal risk.
During this period, GlobalSwitch London East will also be running fail over scenarios during the generator testing, and this will introduce some additional risk as we will be relying on the static ups systems installed on your floors.
AVK to connect/test RMUA at E01/E02/E03 - 1day (31 Oct 2025)
AVK to connect/test RMUB at E01/E02/E03 - 1day (03 Nov 2025)
AVK to connect/test RMUC at E01/E02/E03 - 1day (04 Nov 2025)
AVK to connect/test RMUC at E01 - 1day (05 Nov 2025)
AVK to connect/test RMUE&F at E01/E02/E03 - 1day (06 Nov 2025)
GS OPS to place Ring Feeders E01,E02 & E03 in service on HV-A only and carry out Mains fail test HV-SWB-5A by AVK - 1day (07 Nov 2025)

Isolation of PSS/5/B from Power Station B (10thNovember – 25th November)
AVK to connect/test RMUR at E01/E02 - 1day (17 Nov 2025)
AVK to connect/test RMUE&F at E01 - 1day (18 Nov 2025)
AVK to connect/test RMUD at E01/E02/E03 - 1day (19 Nov 2025)
AVK to connect/test RMUC at E01/E02/E03 - 1day (20 Nov 2025)
AVK to connect/test RMUB at E01/E02/E03 - 1day (21 Nov 2025)
AVK to connect/test RMUA at E01/E02/E03 - 1day (24 Nov 2025)
GS OPS to place Ring Feeders E01,E02 & E03 in service with rings split. AVK to carry out Total Mains Fail Test with rings split - 1day (25 Nov 2025)
Posted Oct 14, 2025 - 07:01 UTC
This scheduled maintenance affects: Taiga Cloud Network (Availability United Kingdom (cluster ndcloud-njoerd)).