Start Campus Portugal Sines - November maintenances

Scheduled Maintenance Report for Taiga Cloud status page

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 01, 2025 - 00:00 UTC

Scheduled

Upcoming maintenances in Start Campus Portugal Sines (November):

Fire Hydrants maintenance - 01/11/2025 00:00 - 04:12 - Fire Hydrant 1-14 - Criticality: Low
Sprinkler Air Compressors - 01/11/2025 00:00 - 01:00 - Air Compressor for dry pipe sprinkler north - Criticality: Low
Lightning Rod - 01/11/2025 00:00 - 01:00 - Lightning Protection Substation - Criticality: Low
Lightning Rod - 01/11/2025 00:00 - 01:00 - Lightning Protection Buffer Vessels - Criticality: Low
Lightning Rod - 01/11/2025 00:00 - 01:00 - Lightning Protection DC-01 - Criticality: Low
Side Stream Filtration - 01/11/2025 00:00 - 01:00 - PCW Side Stream Filter 1-2, Cooling Tower 2-4 Multimedia Filter, Criticality: Low
Air Cooled Chiller - 01/11/2025 00:00 - 02:00 - Air Cooled Chiller 1-2 - Criticality: Low
Cooling Tower/ACS - 01/11/2025 00:00 - 03:00 - Cooling Tower 2-4 - Criticality: Low
Water Cooled Chiller - 01/11/2025 00:00 - 03:00 - Process Cooling Water Chiller 2-4, Criticality: Low
Rear Door Coolers - 01/11/2025 00:00 - 03:36 - RDC.2.P01 - RDC.2.P36 - Criticality: Low
UPS Systems - 01/11/2025 00:00 - 08:00 - UPS B3 module 1-4, UPS B4 module 1-4, UPS B5 module 1-4, Criticality: Low
Generators - Run Tests - 01/11/2025 00:00 - 16:00 - Generator 1-8 - Criticality: Low
Fire Pumps tests - 03/11/2025 00:00 - 01:00 - Sprinkler - Criticality: Low
Cooling Tower/ACS - 03/11/2025 00:00 - 03:00 - Cooling Tower 2-4 - Criticality: Low
Fire Pumps tests - 10/11/2025 00:00 - 01:00 - Sprinkler - Criticality: Low
Cooling Tower/ACS - 10/11/2025 00:00 - 03:00 - Cooling Tower 2-4 - Criticality: Low
Fire Pumps tests - 17/11/2025 00:00 - 01:00 - Sprinkler - Criticality: Low
Cooling Tower/ACS - 17/11/2025 00:00 - 03:00 - Cooling Tower 2-4 - Criticality: Low
Fire Pumps tests - 24/11/2025 00:00 - 01:00 - Sprinkler - Criticality: Low
Cooling Tower/ACS - 24/11/2025 00:00 - 03:00 - Cooling Tower 2-4 - Criticality: Low
Posted Oct 21, 2025 - 09:35 UTC