Scheduled Electrical Power System Maintenance – Lefdal Data Center - Norway

Scheduled Maintenance Report for Taiga Cloud status page

Completed

The scheduled maintenance has been completed.
Posted Feb 24, 2025 - 13:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 24, 2025 - 07:00 UTC

Scheduled

Maintenance Window:
• Power System B: 24th February 2025 – 07:00 to 13:00 GMT

📍 Location & Affected Areas:
• Site: Lefdal Data Center - Norway
• Impacted Areas:
• Data-halls 24 & 25

Scope of Work:
This is a scheduled electrical power system maintenance impacting Power System B. The work includes:
• Power System B is taken down on 24th February
• Temporary loss of uptime on 24th February

This maintenance is essential for power system stability and long-term infrastructure reliability.

Impact & Risk Assessment:
• Temporary downtime (07:00-13:00 GMT)

Mitigation Measures:
• Continuous monitoring during maintenance.
• Immediate response teams on standby.
• For 24th February: Additional cooling contingency measures in place to minimize risks.


Thank you for your patience and cooperation.
Posted Feb 17, 2025 - 13:09 UTC
This scheduled maintenance affected: Taiga Cloud Network (Availability Norway (cluster ndcloud-underground)).