Global Switch - power stream F maintenance

Scheduled Maintenance Report for Taiga Cloud status page

Completed

The scheduled maintenance has been completed.
Posted Feb 13, 2026 - 17:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 13, 2026 - 08:00 UTC

Scheduled

Maintenance date: 13th February 2026 08:00 – 17:00

System Overview:
Recent infrastructure upgrades to migrate the E01 suite infrastructure onto static UPS and generator backed supplies involved the automation of the RMU’s. The testing of the system highlighted a fault on RMU F that needs further investigation from the product manufacturer ( Schneider )
Work Breakdown:
It will be necessary to de-energise power stream F to allow the investigation . The works involve tracing and proving the internal wiring of the RMU and then proving the automated operation of the system. An 8 hour window has been requested but we will aim to complete this task during the morning.
Risk / impact:
Whilst power stream F is isolated – the cabinets supplied from this stream will be running on ‘N’, Failure of other streams connected to these cabinets would result in a loss of supply and breach of SLA
Purpose of Project:
To complete the automation of the RMU’s for autonomous operation in bringing the standby generators on line in the event of utility failure and automatic reinstatement on return.
Systems Impacted:
Loss of redundant supply to power stream F.
Risk Analysis:
Isolation of power stream F will mean the cabinets supplied from this power stream will only have the N supply connected . Back out plan to be included within the MOP to allow prompt as quick as possible return to full resilience.

If you have any concerns during this maintenance window, please contact Taiga Cloud Customer Support via the ticket portal or email cloud-support@taigacloud.com.
Posted Feb 03, 2026 - 14:29 UTC
This scheduled maintenance affected: Taiga Cloud Network (Availability United Kingdom (cluster ndcloud-njoerd)).